Block work progressing well

External block work on the left-hand side of the house

For the last four week or so, while we’ve been blogging about what’s happening inside the house, a team have been working outside laying our block external wall.

This wall surrounds the timber frame and protects it as well as providing a base for rendering and cladding.

It’s been progressing well and has nearly reached the top of the first floor windows. This is good news since the windows are currently scheduled for installation starting next week!