First floor going up

First floor being assembled

A few more days in and the walls of the first floor are being assembled.

Entire wall panels are delivered on trucks and then lifted into position using a crane, where they are then attached to the floor and ceiling. All the external panels are pre-insulated and battened ready for plasterboarding once the house is watertight.

At the bottom of the photo the top of the roof trusses can also be seen. These have been delivered early but will soon be lifted into place to form the roof and loft space.